Donn Screw Up Grid
DONN T37 screw up ceiling grid suitable for constructing
Flush Plaster Ceilings. The system allows for the fixing sheets of plasterboard to the underside of the grid to create a flush plaster gypsum ceiling for skimming
and decorative finish.
GYPTONE INSTALLATION AND JOINTING
Screw Fixing
Gyptone BIG boards with tapered long edges are attached to T37K
Grid using 25mm streaker screws.
The boards have joints filled and the surface painted after fixing and
is
non-removable.
A minimum height of 100mm between slab and grid is recommended for better sound absorption.
System Performance
DonnCeil ceiling systems should be installed in accordance with recommendations described within this brochure. System performance is based on the use of Donn branded components, any substitution of components will compromise performance and cannot be guaranteed and may result in failure under critical conditions.
Installation Conditions
Suspended ceilings form part of the decorative finish of a building and the conditions under which Donn systems are installed must take this into account. The ceiling erection should take place at a late stage in the building contract when the area will be clean and there is less likelihood of damage from other trade
s.
MAXIMUM SPANS OF SUSPENSION ON MAIN TEE
Manufacturers tee shall suspend to maximum of 1200mm.For specialized spans contact the manufacturer for details.
JUNCTION BETWEEN PERIMETER TRIMS AND CEILING GRID Greater than 400mm an additional suspension point should be added in.
PERIMETER TRIMS Perimeter trims - standard suspended ceilings: Perimeter trims for suspended ceilings can be the L-shape or the shadow line type (stepped). Perimeter trims - Flush plaster suspended ceilings galvanized angle or a shadow line type is used to create a shadow line which hides building imperfections. The perimeter trims are measured as an independent item in bills of quantity, as no two areas will necessarily yield the same usage of trims.
TEE SYSTEMS Recommendations for the Suspension of Tee Systems • Subject to loading detail, suspension should not exceed 1200mm centres. • The suspension must not be out of plumb (vertical) more than 25mm for each 150mm of plenum depth and in no case should exceed 500mm to a 3000mm depth. • Whenever above is exceeded and/or when the hanger suspension is more than 2000mm long, then a sub grid is recommended. Should suspension be vertical, then a 4000mm drop would be acceptable using a hangar strap. • In no case should suspension be from other services in the ceiling void. • A hanger suspension point within 400mm from the wall angle or shadow moulding must be installed on main tees & cross tees. • Two steel pop rivets with a shear strength 3 times that of the maximum allowed ceiling load is to be used. • When securing wire to tee, it should be wound tightly around itself at least 3 times. • Should the ceiling mass exceed 20kg/m2, a sub grid is required and a consulting engineer should recommend suitable suspension. Hanger limitations Wire hangers: 2500mm Hanger strap: 4200mm 25x25mm angle hangers: 3600mm
|